Recently a user is purchasing a brand new 75TPH CFB Boiler complete with accessories with the following initial details and specifications.
|
Technical Data |
|
|
Capacity (TPH) |
75 |
|
P (psi) |
972 |
|
T (⁰C) |
480 |
|
Feed water T |
105 |
|
Exhaust Flue Gas T |
150 |
|
Boiler Eff |
86.20% |
|
Primary Air |
137 |
|
Secondary Air |
116 |
|
Blowdown Rate |
5% |
|
Air to Flue Gas |
1.35 |
|
Fuel Req |
10.3 |
|
Pressure requirements for production line: |
|
|
205kpa with steam requirements of around (TPH) |
70 |
|
1136kpa with steam requirements of around (TPH) |
4 |
|
Existing Steam Turbine Data: |
|
|
Steam Pressure Inlet (psig) |
850-950 |
|
Capacity (MW) |
7.5 |